On Friday, May 2, SFSC will receive two large chiller components. These units are oversized, require escorts and special DOT permits for transport. The permit regulates their travel time. The estimated arrival time at the Highlands Campus will be 6 a.m. Delivery takes place via Entrance #4. A 100-ton crane will be used to unload this equipment. To facilitate the delivery, we will shut down Entrance # 4’s roadway until the offload is complete. If you arrive early to work and use this entrance, please understand you may be detoured around the construction area (See Map Below). If you have any questions please feel free to reach out to Derek Bryant in Physical Plant at ext. 7094.